5th/6th/Forest Rose Sewer Separation

Storm Sewer Manhole

FOR MORE INFORMATION CONTACT​:

STEVEN WELLSTEAD, P.E.​
STORMWATER ENGINEER​
121 E. CHESTNUT ST ​
SUITE 100​
LANCASTER, OH 43130​

(740) 687-6614


swellstead@ci.lancaster.oh.us
The City is awarding the contract to Trucco Construction Co., Inc. from Delaware, Ohio in the amount of $2,933,059.00.  Construction has begun as of January 6, 2020 and is expected be completed in Fall 2020.  The tentative schedule is:

​Fifth Avenue (Memorial Dr to High St)                                          January 2020-April 2020
​Forest Rose Avenue (Fifth Ave to Sixth Ave)                                April 2020-May 2020
​Sixth Avenue (Broad St to High St)                                               May 2020-June 2020
​Sixth Avenue (Forest Rose Ave to Columbus St)                          June 2020
​Sixth Avenue (Broad St to alley east of Maywood Avenue)          June 2020-July 2020
​Alley South of Sixth Avenue (Forest Rose Ave to Columbus St)   July 2020
​Testing and Restoration activities                                                  June 2020-September 2020

​This schedule is weather dependent and subject to change based on field conditions.

​Funding for this project is a 0% loan from the Ohio EPA Water Pollution Control Loan Fund (WPCLF) to be repaid by the Stormwater Utility.

Project Area and Plans