2014 Street Paving

Construction Updates
It is important to not that all construction project schedules are dependent on the weather.
Gorsuch Area
Concrete work began on May 27, 2014.
  • 2-3 week projected time frame
  • ADA Ramp upgrades
  • Spot curb repair
Paving work began on June 9, 2014.
  • 2-3 week projected time frame
  • Begin pavement planning / placement
  • Full depth repair areas
Talmadge Area
Concrete work began June 9, 2014.
  • 2-3 week projected time frame
  • ADA Ramp upgrades
  • Spot curb repair
Paving work began June 23, 2014
  • 1 week projected time frame
  • Begin pavement planning / placement
  • Full depth repair areas