Gorsuch Area
Concrete work began on May 27, 2014.
- 2-3 week projected time frame
- ADA Ramp upgrades
- Spot curb repair
Paving work began on June 9, 2014.
- 2-3 week projected time frame
- Begin pavement planning / placement
- Full depth repair areas
Talmadge Area
Concrete work began June 9, 2014.
- 2-3 week projected time frame
- ADA Ramp upgrades
- Spot curb repair
Paving work began June 23, 2014
- 1 week projected time frame
- Begin pavement planning / placement
- Full depth repair areas