Task Name
Duration
Start Date
Finish Date
Intersections SR 37-SR 158 7 days Thursday, May 22, 2014 Friday, May 30, 2014
Ditch Line SR-37 1 day Saturday, May 31, 2014 Saturday, May 31, 2014
Lincoln Avenue - Night work
Mill and Fill - Type 2
5 days Monday, June 2, 2014 Friday, June 6, 2014
Surface SR 37
T-1 Surface
6 days Monday, June 9, 2014 Monday, June 16, 2014
Surface SR 158
T-1 Surface
6 days Monday, June 16, 2014 Monday, June 23, 2014
Surface SR 22
T-1 Surface
6 days Monday, June 23, 2014 Monday, June 30, 2014