State Route Paving
Construction Updates
Task Name |
Duration |
Start Date |
Finish Date |
---|---|---|---|
Intersections SR 37-SR 158 | 7 days | Thursday, May 22, 2014 | Friday, May 30, 2014 |
Ditch Line SR-37 | 1 day | Saturday, May 31, 2014 | Saturday, May 31, 2014 |
Lincoln Avenue - Night work Mill and Fill - Type 2 |
5 days | Monday, June 2, 2014 | Friday, June 6, 2014 |
Surface SR 37 T-1 Surface |
6 days | Monday, June 9, 2014 | Monday, June 16, 2014 |
Surface SR 158 T-1 Surface |
6 days | Monday, June 16, 2014 | Monday, June 23, 2014 |
Surface SR 22 T-1 Surface |
6 days | Monday, June 23, 2014 | Monday, June 30, 2014 |